A custom fitting can be ready to manufacture while the project is still waiting for a finish decision. Equally, material can be available while a sample assessment holds the production release. To plan a useful delivery date, identify which work must finish before the next activity can start, and keep factory readiness separate from arrival on site.
Which delivery date are you planning toward?
Development, factory-ready and delivered dates
Start by naming the event you need to predict. A sample-ready date helps you arrange assessment. A factory-ready date tells you when the finished order can be handed over under its agreed conditions. A delivered date must also account for the applicable transport and receiving arrangements.
These intervals can start from different events. An estimate from the first inquiry is not interchangeable with a production interval that starts after drawings, samples and order conditions are settled. Write the starting event beside the date rather than comparing the numbers alone.
For a refurbishment, the project may care about the date fittings can be received before a room closes for work. Purchasing may instead be tracking when an order can leave the factory. Put both milestones in the same plan so that a seemingly acceptable production estimate is not mistaken for the required site date.
Working days and calendar days
Keep the stated time basis throughout the schedule. Working days depend on the relevant operating calendar; calendar days include the intervening days. Converting either into a promised arrival week needs the actual dates, applicable shutdowns and transport information.
Establish how much custom work is new
An adaptation of an existing platform
An established body with a selected length, source or mounting variation may retain useful production resources. The work still depends on whether the required parts, finish and configuration are established for that order. A familiar appearance gives you little information about their availability.
A changed structure or production resource
A new carrier, optic, housing or dedicated process can add development dependencies. The important distinction is what has to be resolved and made, rather than whether a supplier calls the product standard or custom.
| Requested route | Scheduling question | Useful starting information |
|---|---|---|
| Existing platform with an established option | Which parts and operations are already defined and available? | Exact platform and option/configuration |
| Adapted structure or assembly | Which drawings, samples and changed parts are required? | Changed interfaces and usable host dimensions |
| New dedicated part or process | What must be developed before representative supply can proceed? | Required output and the new production resource |
The wider custom-lighting development process explains the outputs of these stages. For scheduling, connect each output to the work that actually needs it.

Find the conditions that start each clock
Technical information and order conditions
Ask what makes the inputs usable: the current drawing, selected construction, required assessment and the applicable commercial release conditions. If the supplier is waiting for a missing host dimension, the inquiry date alone does not establish that development has started.
Keep buyer decisions in the plan as activities too. The elapsed time between a sample reaching the buyer and a usable assessment returning to the supplier can affect production readiness even when no factory operation changes.
Use published ranges within their scope
VST’s published custom-lighting planning guidance distinguishes light and high customization. It lists sample planning ranges of 15โ25 and 30โ50 working days respectively, and bulk-production ranges of 20โ30 and 25โ35 working days. Those are company-published planning ranges, subject to the actual construction, usable technical inputs and applicable order conditions; they are not an accepted schedule for every model.
Read the relevant quotation’s starting conditions before using such a range. The calculation below uses its own assumed activity durations, not a reconstruction of those company ranges.
Which activities can overlap?
Work with an independent input
Two activities can run together when each has what it needs to proceed. For example, an agreed material selection might allow preparation to begin while a representative sample is assessed. That requires an accepted advance-preparation basis; it cannot be inferred from a drawing merely being available.
Choices that still depend on a decision
If sample assessment could change the carrier, finish or optical part, preparing that item early creates a change risk. Specify which choices are fixed and which remain open. Otherwise an apparently shorter plan may depend on material that cannot be used after the next decision.
Consider a decorative housing whose color has been selected but whose joint detail is unresolved. Color selection may support some preparation; it does not establish that every fabrication step can proceed. Follow the actual dependency rather than treating the whole housing as either ready or blocked.

Build a dependency table before adding durations
Duration, predecessor and finish
For each activity, record its duration and required predecessor. A following activity waits for the latest of the inputs it needs. Adding every duration gives the finish only when all those activities genuinely occur in sequence.
| Activity | Assumed duration | Baseline predecessor |
|---|---|---|
| Drawing review | 5 working days | Usable initial inputs and release conditions at Day 0 |
| Sample build | 20 working days | Drawing review complete |
| Buyer assessment | 5 working days | Sample build complete |
| Material preparation | 25 working days | Buyer assessment complete in the sequential baseline |
| Production | 25 working days | Assessment and material preparation complete |
| Inspection and packing | 5 working days | Production complete |
The boundaries of the example
Every duration in this exercise is assumed. Day 0 means the example’s initial technical and order conditions are already met. The relative schedule excludes freight and does not convert to a calendar with unspecified holidays.
The finish calculation is simple: earliest start equals the latest finish of the required predecessors; earliest finish equals that start plus the activity duration. This makes an overlap or delay testable without hiding it inside a single delivery estimate.
Work through one development-to-dispatch schedule
A sequential baseline
In the baseline, drawing review runs from Day 0 to Day 5. Sample build then finishes at Day 25, followed by buyer assessment at Day 30. Material preparation starts only after that assessment and ends at Day 55.
Production runs from Day 55 to Day 80. Inspection and packing take the example to Day 85, its factory-ready milestone. Calling this a dispatch-planning result still assumes that any separate handover or release conditions are met; no transport time has been added.
A specifically permitted overlap
Now change one condition: after drawing review, the relevant material choice is fixed and advance preparation is explicitly accepted. Material preparation can run from Day 5 to Day 30. Sample build runs from Day 5 to Day 25, and buyer assessment follows from Day 25 to Day 30.
Both required production inputs are now ready at Day 30. Production ends at Day 55 and inspection/packing at Day 60. The 25-working-day difference comes from this specific permitted overlap. It is not a reduction that follows automatically from ordering custom lighting.
The choice also has a practical consequence: advance preparation commits work before the assessment is complete. Whether that is appropriate depends on what the assessment can still change and the terms accepted for the prepared material. The earlier finish should be considered alongside that exposure.
Use the two paths to ask a precise scheduling question: can this particular preparation proceed from the drawing release, or must it wait for the assessment? A general request to make everything faster does not resolve that dependency.

Trace a design or approval change to the affected work
A delay on a required predecessor
Return to the overlap case and extend buyer assessment by 5 working days. It now ends at Day 35, although material remains ready at Day 30. Production must wait until Day 35, finish at Day 60, and complete inspection/packing at Day 65.
The buyer-side delay has moved the factory milestone because it now controls the production start. It has not extended every activity by 5 days.
Locate the decision that produces a usable assessment. A request for a different finish or mounting detail may be a design change, while a delayed response to an unchanged sample is a decision delay. Both affect the plan, but they do not necessarily require the same work to be repeated.
A change that invalidates prepared material
If assessment changes a part already being prepared, identify the affected work and its new input. Some preparation may remain usable while another item needs replacement or revision. The custom-lighting change-management resource addresses that specification task.
Update the schedule from the changed dependency. Neither resetting all work nor assuming no effect gives a reliable new finish.
Plan phased dispatch without assuming finished stock
A production batch and a delivery release
A smaller requested shipment may help your receiving plan, but its fittings still need to be made and ready. Distinguish the manufacturing batch from the quantity handed over in each release.
Ready quantities, identification and packing
| Release question | Readiness condition | Effect if unresolved |
|---|---|---|
| Which variants leave together? | The required quantities of those variants are complete | A total count can hide a missing item |
| Can the items be released? | Applicable inspection and commercial release conditions are met | Finished production alone may not permit handover |
| Can receiving identify the contents? | Packing and item references match the release grouping | Products can arrive without usable allocation |
Material reservation for an agreed repeat-supply arrangement is also different from finished stock. Reserved inputs may support a later production run, but they have not necessarily passed through assembly, inspection and packing.
For a phased project, state the proposed quantities and delivery groups, then locate their actual readiness points. Do not assume that splitting one total into two shipping instructions creates two earlier production completions.
A first release containing only one variant can also leave a project unable to complete its intended area. Match the release composition to the receiving task: which fittings, mounts and separately supplied equipment must be available together? The answer can matter more than the total number of cartons dispatched.

Decide whether expediting moves the finish date
Shortening the controlling path
An expedited activity helps the final date when the reduction changes a dependency that controls the finish. Recalculate the following work instead of subtracting the advertised time saving from the final date automatically.
A faster item that was not holding production
In the Day 60 overlap case, shorten material preparation from 25 to 20 working days. It now finishes at Day 25. Buyer assessment still finishes at Day 30, so production starts at Day 30 and the factory-ready milestone remains Day 60.
The material is earlier, but the final result is unchanged. This is a useful test before paying for a proposed rush arrangement: which finish-controlling activity changes, and what revised result follows? Any actual expedite option still needs an applicable offer and must retain the required inspection and release work.
If the latest predecessor changes, calculate again. Material preparation might control a different order even though it does not control this example. An expedite decision therefore belongs to the current dependency schedule, not to a permanent rule that samples or materials are always the slowest part.

Turn the factory-ready result into a purchasing timeline
The date the supplier can actually confirm
Keep the calculation’s basis with the result: route, usable starting inputs, required decisions, permitted overlaps and the handover milestone. For custom-lighting supply, that is a more useful discussion than a request for one typical number covering every stage.
Transportation and site readiness
| Milestone | Required planning source | Current exercise |
|---|---|---|
| Factory-ready | Applicable supplier schedule and release basis | Assumed Day 85 or Day 60 under the stated route |
| Carrier handover and transit | Applicable booking, route and transport terms | Not provided |
| Receiving and site availability | Project receiving and site arrangements | Not provided |
Use the actual carrier and receiving information to work from factory readiness toward the needed-on-site date. Until that information exists, the remaining duration is unknown, not zero. You can still make a sound purchasing decision by knowing which milestone is supported and which additional dependency must be resolved.